Uong Bi Thermal Power Plant — 330 MW · UPS Life Extension

11 years serving Uong Bi Thermal Power Company — contributing to its success to this day.

Life Extension of an EXCOR APODYS2 UPS at Uong Bi 330MW Power Plant, combining electronics modernization, power-stage refurbishment and full functional testing.

SECTORUtilitiesAPPLICATIONThermal Power Generation / AC UPS Life Extension & Battery Capacity TestingREFERENCE HISTORY2020–2023
← BACK TO PROJECTS & REFERENCES
Hoppecke vented battery at Uong Bi 330 MW — EDPN site survey, October 2013
END USERUong Bi Thermal Power Company (EVNGENCO1) - Uong Bi 330 MWSITE / PROJECTUong Bi Thermal Power Plant — 330 MW unit, Uong Bi, Quang Ninh
INSTALLED-BASE LIFECYCLE

From factory to Life Extension.

One installed base, followed through its life — who did what, and when.

2009
Manufactured

Chloride APODYS2 UPS and UPS / inverter built for the 330 MW unit.

OEM · CHLORIDE
2010
In operation

Systems in operation with the 330 MW unit (as-built February 2010).

PLANT
2013
Site survey

EDPN site survey of the 220 VDC Hoppecke battery.

EDPN
2020
First EDPN service

Capacity testing and recovery of the 220 VDC Hoppecke battery.

EDPN
2023
Parts & PM

Spare parts and preventive maintenance for the UPS and UPS / inverter.

EDPN
2023
Life Extension

APODYS2 → CP70Z-generation electronics, touch-screen HMI, full UPS test in December.

EDPN
Manufacturer / plantEDPN
PROJECT

EXCOR APODYS2 upgraded with CP70Z-generation electronics and new HMI.

Life Extension engineering, site preparation, electronics modernization, inverter-stage refurbishment, component replacement, HMI upgrade and full UPS testing.

Life ExtensionRetrofit / ModernizationFull TestingSpare PartsPreventive MaintenanceBattery Capacity Testing & Recovery
THE REQUIREMENT

What the site needed.

The EXCOR APODYS2 UPS had been in operation since 2010 and required a structured Life Extension path rather than routine spare-parts replacement alone.

EDPN SCOPE

What EDPN delivered.

EDPN upgraded the legacy EXCOR APODYS2 platform to CP70Z-generation electronics with a color touch-screen HMI, refurbished the inverter stage, replaced key control and power components, and completed full UPS testing. EDPN also supplies spare parts and preventive maintenance for the 330 MW unit UPS and UPS / inverter, and carried out capacity testing and recovery of the 220 VDC Hoppecke vented lead-acid battery.

PROJECT HISTORY

Project history.

2010
Original installed base

EXCOR APODYS2 UPS put into operation.

2013
Site survey

EDPN site survey of the 220 VDC Hoppecke vented lead-acid battery (October 2013).

2020
Battery capacity testing & recovery

Capacity testing and recovery of the 220 VDC Hoppecke vented lead-acid battery.

2022–2023
Life Extension planning

Site survey and upgrade engineering for the legacy platform.

2023
Modernization execution

CP70Z-generation electronics, touch-screen HMI, inverter-stage refurbishment and critical component replacement.

2023
Spare parts & preventive maintenance

Spare parts supply and preventive maintenance for the UPS and UPS / inverter of the 330 MW unit.

Dec 2023
Full UPS test

Full functional testing completed to confirm UPS operation and capability.

RESULT

What followed.

The Life Extension work was completed with full functional testing of the upgraded UPS.

2013 · SITE SURVEY

220 VDC vented lead-acid battery of the 330 MW unit.

EDPN site photos, October 2013.

Hoppecke vented lead-acid cells (2013)
Hoppecke vented lead-acid cells (2013)
220 VDC battery strings in the battery room (2013)
220 VDC battery strings in the battery room (2013)
Battery string terminal cables (2013)
Battery string terminal cables (2013)
Hoppecke vented lead-acid cell label (2013)
Hoppecke vented lead-acid cell label (2013)
NEW PROJECT OR INSTALLED EQUIPMENT?

Tell us about the application.

For a new project, send the specification or load requirement. For service support, send the site, model, serial number, alarm or condition, and available maintenance history.